Agenda
- PCC Updates
– Ryan Ragaza-Bourassa
- 2022 CRISI Grant – Phase II
- Project 1 – CW Branch ($48M): Geiger Spur (MP 8) to Davenport (MP 40.6)
- Construction Update – SLD, switch ties, and right of way cleanup.
- Project 2 - P&L Branch ($25M): Marshall (MP 1) to Garfield (MP 49)
- Pre-con meeting on March 24th.
- Railworks requested to suspend working days. Construction will start on May 15th.
- Project 3 – PV Hooper Branch ($39M): Hooper to Winona/Winona to St. John
- Design Update – Started PS&E development, working toward 60% design. Looking to add $10M to this project due to projects
1 and 2 being underbid.
- 2024 CRISI Grant – Phase III
- Project 4 – CW Branch ($58M): Davenport to Wilbur
- FRA completed Attachment 2 review last week. WSDOT submitted updated draft yesterday.
- Expect to be obligated in the a month or two.
- WSDOT submitted Attachment 2 to FRA for review in November 2025.
- 2026 CRISI Grant – Phase IV
- Project 5 – CW Branch ($45M): Wilbur to Hanson
- 19-mile improvement project
- Waiting on NOFO announcement. Division’s GEC, HNTB, will be drafting the application.
- Paul Katovich (HighLine Grain CEO) is reaching out to stakeholders for financial and letters of support.
- Estimate complete and working on 30% Preliminary Plans
- BLPI/WIMRY Update
- RRB1233 Amendment 7 – Leased Property Revision
- Executed last month.
- BLPI/WSDOT operating lease agreement
- Executed last month.
- WIMRY will submit the executed agreement to STB to be an approved operator in Washington. WIMRY’s attorney is preparing
to submit to STB. Typically, it takes 30 to 45 days for approval.
- SS&P/WIMRY Interchange Agreement
- SS&P and WIMRY are working on amending the interchange agreement.
- Colfax Noise Issue – WATCO Rail Yard
- Siding Update (CW Branch)
- Siding derailment in Davenport, April 1st.
- Ties and surfacing would help resolve the gauge issue. Scheduling a workshop with HighLine and WER in May to discuss
the issues, subleases, and develop a short and long-term strategy.
- Palouse SR 27 rail crossing and retaining wall status update.
- Rail Crossing – Meeting with the Region Traffic and Signal Office later this month.
- Retaining Wall – Bridge Office recommended that Geotech will provide the effort to evaluate the wall.
- Procuring a firm to perform boundary survey to confirm ownership.
- Geotech provided a scope of work for drilling 10 boring holes, 5 behind and 5 in front of the wall, testing, analyzing
the borings, and drafting a report.
- Not in the PCC budget, but would need to be a legislative ask and the earliest money would be available July 1,
2027.
- LaCrosse Bunkhouse
- Waiting on Port of Whitman to send back the documents signed with checks to pay for recording.
- Kara requested a right of entry permit to perform a Phase I Environmental Site Assessment to establish a baseline
prior to Port ownership, so that any cleanup could have access to funding support.
- WSDOT issued ROE permit on 12/18/25.
- Shawnee Bridge Insurance Claim
- Received a settlement proposal of $505,000
- WSDOT’s quote to replace the bridge was $2.6M to cover design and construction costs.
- Working with Risk Management to review the proposal.
- Spokane County Coulee Hite Railroad Crossing Safety Project
- April Ad date and construction will be in June or October to avoid impacting harvest.
- Open Discussion –
All
- 2026 Rail Authority Meeting Schedule:
-
April 29, 2026 at the Eastern Region Spokane County Room from 1:00 – 2:00 pm.
-
July 15, 2026 at Lincoln County from 1:00 – 2:00 pm.
-
October 14, 2026 at McGregor’s Facility from 1:00 – 2:00 pm.
________________________________________________________________________________
Microsoft Teams meeting
Join:
https://teams.microsoft.com/meet/29147569724185?p=BIWyV6VXm8YOLXE9Sf
Meeting ID:
291 475 697 241 85
Passcode:
Up99Qj27
Need help?
|
System reference
Dial in by phone
+1 206-531-0324,,334531677#
United States, Seattle
Find a local number
Phone conference ID:
334 531 677#
For organizers:
Meeting
options |
Reset dial-in PIN
________________________________________________________________________________
Attachments
Loading community reactions…