- Jordan Neal, Robert Maiorino, Lynda Walker, Daniel Baker, Brenna Carveth, Dave Istrate, Steven Forster, Jeremy R. Gratz,Public Works Submittals,Lorri Corcoran,Ryan Sheehan, zane.prescott@dnr.wa.gov, R1planning@dfw.wa.gov, jamie.kowalski@us.af.mil, 92ces.cen.communityprojcoord@us.af.mil, tmourning@cityofcheney.org,Heather Trautman, matthew.mccain4@us.af.mil, Corey T. Smith,Development Services Center Permit Team,Commercial Projects, todd.mclaughlin@avistacorp.com
Hello~
There is a preapplication meeting scheduled on 12/02/25 at 10 am in person at the Spokane County Building and Planning Department. If you're unable to attend in person, please join us with the teams link provided.
This proposal involves constructing a new 230 kV transmission line between the future Bluebird Substation and Garden Springs Substation, approximately 12 miles.
Thank you,
Christine Fidler
Project Coordinator 2
Spokane County Building and Planning
509-477-7240
________________________________________________________________________________
Microsoft Teams Need help? https://aka.ms/JoinTeamsMeeting?omkt=en-US
Join the meeting now https://teams.microsoft.com/l/meetup-join/19%3ameeting_Y2EzMTk0OTMtYmZiOS00MjJlLWEyNWEtNjJkNDcxNjk4NTE2%40thread.v2/0?context=%7b%22Tid%22%3a%224a1f23f8-6124-475a-9dd1-a66dc3f779bc%22%2c%22Oid%22%3a%222e757b84-3088-4876-b8d9-e4bd0c2a2f38%22%7d
Meeting ID: 244 031 012 217 87
Passcode: EH6QV9Vd
________________________________
For organizers: Meeting options https://teams.microsoft.com/meetingOptions/?organizerId=2e757b84-3088-4876-b8d9-e4bd0c2a2f38&tenantId=4a1f23f8-6124-475a-9dd1-a66dc3f779bc&threadId=19_meeting_Y2EzMTk0OTMtYmZiOS00MjJlLWEyNWEtNjJkNDcxNjk4NTE2@thread.v2&messageId=0&language=en-US
Org help https://cp.spokanecounty.org/images/countylog/MeetingHelp.Html | Privacy and security https://cp.spokanecounty.org/images/CountyLogo/Legal.html
________________________________________________________________________________
Attachments